Work on replacement of the Solsqua-Sicamous bridge is underway. (File Photo)

Work on replacement of the Solsqua-Sicamous bridge is underway. (File Photo)

Solsqua-Sicamous Bridge work on pace for June 2021 completion

Replacement of the 100-year-old span began last August.

If work on the bridge replacement project continues as planned, drivers can expect to be crossing the Eagle River using a new Solsqua-Sicamous Bridge by June.

An update delivered to Sicamous’ council at its Feb. 24 meeting by Brandon Barker from ISL Engineering suggested about 62 per cent of the project remained unfinished, leaving around three months of work to go.

The report from the engineering firm stated that pre-cast bridge girders for the new span were on site and ready for placement. There were still several inspections the bridge must pass before the completion of the project. Sicamous operations manager Joe McCulloch told council he was happy with the progress on the project and that he believed the new bridge will be finished by its May 31 deadline, and within its estimated budget.

Read More: Sicamous receives $4.8 million in grant funding for infrastructure projects

Read More: Bridge replacement to get underway in Sicamous

Once the new bridge is finished, removal of the old bridge and its pilings is expected to continue until the end of 2021.

Full extraction of the old bridge’s pilings was not part of the original contract, but it is being required by Transport Canada. According to ISL’s report to council, the contractor working on the bridge replacement thinks that full removal of the old pilings can be accomplished for about $33,000.

According to Barker, removal of the old bridge piling and other in-stream works will likely have to wait until November or December 2021. The delay is because work in fish-bearing streams are only permitted by the government at certain times of year.

Read More: Shuswap auto recycler breaks out of Rust Valley for Backroad Truckers

Read More: New video promotes Salmon Arm staples of agriculture, food production

Construction cost for the bridge was estimated at $4,556,949. The district received a $4.5 million federal government grant in 2018. For related professional services, including engineering, the cost was estimated at $1,286,669. With some variability on the actual costs to complete the project, the final total cost is estimated to be up to $5.84 million.

Along with the federal grant, a financial report to council anticipated $720,000 would be spent from the district’s bridge reserves, as well as $449,936 from the community works fund.

Mayor Terry Rysz compared the current progress to the state of things eight or nine years ago, when it was clear the nearly 100-year-old the bridge would need to be replaced soon but no one was sure how they would pay for it.



jim.elliot@saobserver.net

Like us on Facebook and follow us on Twitter

Sicamous

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Windsurfers enjoying a windstorm on Skaha Lake in Penticton on March 28, 2021. (Sandy Steck Photography)
Wind warning issued for Okanagan Valley

Boaters are being warned of gusts up to 70 km/h by late afternoon on Sunday

Vernon Vipers forward Ryan Shostak (centre) fends off a check from Salmon Arm defenceman to get a close-in scoring attempt on Silverbacks goalie Owen Say during Vernon’s 3-2 B.C. Hockey League pod play shootout victory Saturday, April 17, at Kal Tire Place. (Lisa Mazurek - Vernon Vipers photography)
Vernon Vipers use shootout to subdue Salmon Arm

Snakes score 3-2 B.C. Hockey League pod play win at Kal Tire Place

Coldstream Fire Department crews stationed at Kal Lake Provincial Park parking lot on Cosens Bay Road on Sunday, April 18, after a car went over a cliff in the area. (Roger Knox - Morning Star)
Driver escapes after car goes over cliff in Coldstream near Kal Lake Park

The driver has been transported to hospital with unspecified injuries

A GoFundMe page has been launched for a Vernon man whose BX orchard property home off Pleasant Valley Road near Stickle Road was totally destroyed in a fire Saturday, April 17. (Brendan Shykora - Morning Star)
Fundraising campaign launched for Vernon man who lost home to fire

A GoFundMe page has been started by family; man taken to hospital with injuries from fire

Each spring, the Okanagan Fest-of-Ale is held in Penticton. This year, as a result of the COVID-19 pandemic, the festival will not be held. However, beer is still available. How much do you know about this beverage? (pxfuel.com)
QUIZ: How much do you really know about beer?

Put your knowledge to the test with this short quiz

Vancouver resident Beryl Pye was witness to a “concerning,” spontaneous dance party that spread throughout social groups at Kitsilano Beach on April 16. (Screen grab/Beryl Pye)
VIDEO: Dance party erupts at Vancouver’s Kitsilano Beach to the dismay of onlookers

‘It was a complete disregard for current COVID-19 public health orders,’ says Vancouver resident Beryl Pye

Deputy Prime Minister and Minister of Finance Chrystia Freeland responds to a question during Question Period in the House of Commons Tuesday December 8, 2020 in Ottawa. The stage is set for arguably the most important federal budget in recent memory, as the Liberal government prepares to unveil its plan for Canada’s post-pandemic recovery even as a third wave of COVID-19 rages across the country. THE CANADIAN PRESS/Adrian Wyld
Election reticence expected to temper political battle over federal budget

Opposition parties have laid out their own demands in the weeks leading up to the budget

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

A Kelowna Pride Festival 2019 participant holds up a flag. (Kelowna Pride Society)
Kelowna Pride, RCMP continue to work on ‘Safe Place Program’

A new committee has been formed to refine the ‘Safe Place Program’ created by the Kelowna RCMP

Join Black Press Media and Do Some Good
Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

A strange odour at a West Kelowna apartment building prompted the evacuation of 150 residents on Sunday morning, April 18. (Aaron Hemens - Capital News)
Strange smell at West Kelowna apartment prompts evacuation of 150 residents, pets

150 residents ordered evacuated from a West Kelowna apartment building early Sunday morning

This is what’s left of a truck that caught fire at Pyramid Provincial Park off Highway 97 near Summerland Saturday night. (Monique Tamminga Western News)
Photo Gallery: Truck gutted by fire at popular Okanagan park, trees saved

Just a metal shell of what once was a pick up truck is left at the scene

A syringe is loaded with COVID-19 vaccine at a vaccination clinic run by Vancouver Coastal Health, in Richmond, B.C., Saturday, April 10, 2021. THE CANADIAN PRESS/Jonathan Hayward
B.C. to open up COVID vaccine registration to all B.C. residents 18+ in April

Registration does not equate to being able to book an appointment

(Black Press file photo).
UPDATED: Multiple stabbings at Vancouver Island bush party

Three youths hospitalized after an assault in Comox

Most Read